  • What Is A Work Breakdown Structure?

    什麼是工作分解結構?

  • Hello, I'm Jennifer Whitt, director at projectmanager.com.

    大家好,我是 Projectmanager.com 的總監珍妮弗-惠特(Jennifer Whitt)。

  • Well, welcome to our whiteboard session today on what is a work breakdown structure.

    歡迎參加我們今天的白板會議,瞭解什麼是工作分解結構。

  • So, a lot of times we get questions from the forum and other sources of people calling in really trying to understand what the work breakdown structure is.

    是以,我們經常會從論壇和其他管道收到一些人打來的電話,詢問工作分解結構是什麼。

  • And there's so much confusion out there because it gets tied into maybe a software tool or other aspects.

    由於可能與軟件工具或其他方面聯繫在一起,是以存在很多混淆。

  • And people can't determine what's the difference between that and a schedule and other parts of the project.

    人們無法確定這與進度表和項目的其他部分有什麼區別。

  • So, I want to take the time out on this whiteboard session just to clarify what the work breakdown structure is.

    是以,我想在這次白板會議上花點時間說明一下什麼是工作分解結構。

  • Well, you know me, I'm big on terms and I like to be clear and go forward on a real definition of terms.

    你知道我的,我很注重術語,我喜歡把術語說清楚,並對術語進行真正的定義。

  • So,

    那麼

  • a lot of times you'll see me on the whiteboard sessions reference my good friend Google.

    很多時候,你會看到我在白板會議上提到我的好朋友谷歌。

  • Well,

    好吧、

  • in this case,

    在這種情況下、

  • I'm referencing

    我指的是

  • a guide.

    指南。

  • A guide

    指南

  • to the Project Management Body of Knowledge by PMI and this specifically is the fourth edition.

    項目管理知識體系》,特別是第四版。

  • Many times I see the teams get confused because they lose track of, they lose essence of, why are we doing this project?

    很多時候,我看到團隊感到困惑,因為他們失去了方向,失去了本質,我們為什麼要做這個項目?

  • And specifically the reason we're doing a project is to produce the deliverables.

    具體來說,我們之所以要做一個項目,就是為了交付成果。

  • So,

    那麼

  • this is a very important piece.

    這是一篇非常重要的文章。

  • And if you can create a work breakdown structure from the beginning and identify the deliverables being produced when, then that a picture truly is worth a thousand words for not only you the project manager, but your team, it sets the vision again for the project objectives.

    如果你能從一開始就創建一個工作分解結構,並確定在什麼時候交付成果,那麼對於你這個項目經理和你的團隊來說,一張圖片真的勝過千言萬語,它再次為項目目標設定了願景。

  • So, let's take a look at the purpose.

    那麼,讓我們來看看目的何在。

  • The purpose again is to organize and define the total scope.

    目的還是組織和確定總體範圍。

  • So, the scope is comprised of the deliverables.

    是以,範圍由可交付成果組成。

  • So, this hierarchical decomposition of the work,

    是以,這種分層分解的工作、

  • uh, it looks like this.

    呃,看起來是這樣的

  • Here's a graphical picture.

    下面是一幅圖表。

  • So, here's just generically,

    所以,這裡只是泛泛而談、

  • you can take these this generic hierarchical structure and begin breaking it down for your own.

    你可以利用這種通用的分層結構,並開始將其分解為你自己的結構。

  • So, here's a project and in this specific one,

    是以,這裡有一個項目,而且是一個特殊的項目、

  • uh, you may work on uh projects that include phases.

    呃,您可能會參與包括階段性工作在內的項目。

  • So, there may be a phase one, phase two or other multiple phases.

    是以,可能會有第一階段、第二階段或其他多個階段。

  • This one has two phases and a deliverable, a main high high level deliverable produced.

    這個項目有兩個階段和一個交付成果,一個主要的高水平交付成果。

  • And this also has sub projects, so this also can include sub projects that are broken down as well.

    這還包括子項目,是以也可以包括細分的子項目。

  • But if you look at phase one and break down this, this has two deliverables beneath the phase, so it's producing two main deliverables.

    但是,如果你看一下第一階段並將其分解,這個階段下有兩個可交付成果,所以它產生了兩個主要的可交付成果。

  • And so we look at what's the work required to produce these deliverables.

    是以,我們要看看生產這些可交付成果需要做哪些工作。

  • So, we keep breaking it down, we break it down to the work.

    是以,我們要不斷分解,分解到工作中去。

  • The work, the work to be executed, so work is executed by work packages.

    工作,即要執行的工作,是以工作是通過工作包來執行的。

  • So, this deliverable one is broken down to other sub deliverables and which are broken down eventually to work packages.

    是以,第一項可交付成果被分解為其他子可交付成果,而這些子可交付成果最終又被分解為工作包。

  • And remember, your team members are completing work packages

    請記住,您的團隊成員正在完成工作包

  • that produce these deliverables.

    產生這些交付成果。

  • And again, this can continue to be broken down.

    這一點還可以繼續細分。

  • But this simply is a work breakdown structure, I think it's very important to understand the definition and the structure, the purpose and how we do this.

    但這只是一個工作分解結構,我認為了解其定義和結構、目的以及我們如何做到這一點非常重要。

  • Truly, a picture is worth a thousand words.

    真可謂一圖勝千言。

  • And I hope this one helps you for your teams and your projects.

    希望這篇文章能對你的團隊和項目有所幫助。

  • At projectmanager.com, we believe firmly in work breakdown structures and that they do and can create a picture that's worth a thousand words for you and your team.

    在 projectmanager.com,我們堅信工作分解結構,它們能夠為您和您的團隊創造出勝過千言萬語的畫面。

  • So, if you need a tool that can help you decompose the work done on your project, then sign up for our software at projectmanager.com.

    是以,如果您需要一款能幫您分解項目工作的工具,請登錄 projectmanager.com 註冊我們的軟件。